⚡ Electrical Design ⚡
Part -1
🔷 Introduction
Electrical design is a critical part of any project, ensuring safe, reliable, and efficient power distribution. Proper calculation of load, transformer capacity, cable sizing, protection devices, and panel design is essential for successful project execution.
This article explains a practical example of electrical design calculation in a simple step-by-step method suitable for engineers, students, and site professionals.
🔷 Design Data (Assumed)
- Total Connected Load = 500 kW (Detail break-up at last)
- Demand Factor = 0.7
- Power Factor (PF) = 0.9
- System Voltage = 400 V (3-phase) { 3 phase voltage in India: 400V ±10% → 360V to 440V}
- Single-phase voltage: 230V ±10% → 207V to 253V
1. Line-to-Phase (Neutral) Voltage
For :
2. Power in a 3‑Phase System
- Active Power (Real Power):
- Reactive Power:
- Apparent Power:
Where:
= Line-to-line voltage (400 V here)
= Line current
= Power factor
🔷 Load Estimation
Maximum Demand = Connected Load × Demand Factor
= 500 × 0.7
= 350 KW
Apparent Power (KVA)
✅ KVA Calculation
S = P / PF
= 350 / 0.9
= 389 KVA
✔ Maximum Demand = 350 KW
✔ Required Capacity = 389 KVA
👉 Always consider future expansion (10–20%) in design.
🔷 Transformer Sizing
The transformer should be selected above the calculated load.
Required Capacity = 389 KVA
✅ Transformer Selection Formula
(Safety Factor = 1.1 to 1.25)
Example:
389 KVA × 1.25 ≈ 486 KVA
👉 Select Standard Rating = 500 KVA
👉 Reason:
- Standard rating
- Provides margin for future load
- Prevents overloading
🔷 DG (Diesel Generator) Sizing
DG set is selected to supply essential loads during power failure.
✅ DG KVA Calculation
OR
🔹 Example
Assume:
Essential Load = 300 kW
Power Factor = 0.8
Add 15–20% margin:
375 × 1.2 = 450 KVA
👉 Select Standard DG = 500 KVA
🔷 Important DG Considerations
✔ Starting current of motors
✔ Voltage dip during starting
✔ Future expansion
✔ Fuel consumption
✔ Synchronization (if multiple DGs)
🔷 Cable Sizing
Load Current Calculation
Ib = P / (√3 × V × PF)
= 350,000 / (1.732 × 400 × 0.9)
≈ 560 A
✔ Design Current ≈ 560 A
✅ Select Cable Current Rating (Iz)
As per IS:
But in practical design:
Now refer to IS 3961 / IS 7098 tables for 1.1 kV XLPE cable.
Option 1: Copper (Cu) XLPE Cable
Typical current capacities (approx., 40°C air, single cable):
| Size (Cu XLPE) | Current Capacity |
|---|---|
| 300 mm² | 520–560 A |
| 400 mm² | 600–650 A |
| 500 mm² | 680–730 A |
👉 For 700 A requirement:
✔ 400 mm² → Marginal
✔ 500 mm² → Safer
✅ Apply Derating Factors
Derating required for:
- Ambient temperature
- Grouping of cables
- Method of laying
- Underground installation
Example:
If derating factor = 0.9
Effective capacity of 400 mm²:
❌ Not adequate for 700 A
So increase to 500 mm².
✅ Voltage Drop Check (IS 732 Requirement)
Voltage drop should be within:
- 3% for power circuits
- 5% total system
Voltage Drop:
If VD exceeds limit → Increase cable size.
✅ Short Circuit Withstand Check
As per IS 7098:
Where:
- Isc = Short circuit current
- t = Fault clearing time
- k = Material constant
Cable must withstand system fault level.
🔷 Final Decision
For 560 A load:
✔ After applying 25% margin → 700 A required
✔ After derating → 400 mm² insufficient
✔ 500 mm² Cu XLPE preferred
OR
✔ Two runs of 300 mm² in parallel
Option 2: Aluminium (Al) XLPE Cable
Aluminium has lower conductivity (~61% of Copper). So larger size is required.
Typical Current Capacity:
| Size | Current Capacity |
|---|---|
| 400 mm² | 450–500 A |
| 500 mm² | 520–560 A |
| 630 mm² | 580–620 A |
| 800 mm² | 650–700 A |
👉 For 700 A requirement:
✔ 630 mm² → Marginal
✔ 800 mm² → Recommended
✅ Apply Derating Factors (Mandatory as per IS 732)
Derating due to:
- Ambient temperature
- Grouping
- Buried installation
- Soil thermal resistivity
Example:
If derating factor = 0.9
For 630 mm² Al:
❌ Not sufficient
For 800 mm² Al:
✔ May still require parallel cables depending on condition.
✅ Voltage Drop Check
Voltage Drop:
Since Aluminium has higher resistance:
✔ Voltage drop will be higher
✔ Cable length becomes critical
If VD > 3% → Increase cable size
✅Short Circuit Withstand Check (IS 7098)
k value:
- Copper ≈ 143
- Aluminium ≈ 94
👉 Aluminium requires larger cross-section for same fault level.
🔷 Final Comparison (Practical Selection)
| Parameter | Copper | Aluminium |
|---|---|---|
| Conductivity | High | Lower |
| Size Required | Smaller | Larger |
| Cost | Higher | Lower |
| Voltage Drop | Lower | Higher |
| Short Circuit Strength | Better | Lower |
| Termination | Easy | Needs Bimetallic Lugs |
🔥 Final Engineering Decision (For 560 A Load)
| Material | Recommended Size |
|---|---|
| Copper | 500 mm² |
| Aluminium | 800 mm² |
OR
✔ Two runs of smaller cables in parallel.
🔹 Important Checks for Cable Selection
✔ Current carrying capacity
✔ Voltage drop (must be within limits)
✔ Short-circuit withstand capacity
✔ Installation method (tray, duct, buried)
✔ Derating factors (temperature, grouping)
🔷 Protection Device Selection
Breaker Rating
Breaker Current ≥ 1.25 × Ib
≥ 1.25 × 560
≈ 700 A
✔ Selected Breaker = 800 A ACB
👉 Provides:
- Safe operation
- Protection against overload & short circuit
Breaking Capacity
✔ Icu Rating = 50 kA (Typical value)
👉 Must be selected based on fault level calculation.
🔷 Busbar Design
🔹 Busbar Sizing
Busbar is the main current-carrying conductor inside LT panels.
It must be designed based on:
✔ Rated Current
✔ Short Circuit Level
✔ Temperature Rise
✔ Material (Copper / Aluminium)
🔹 Step 1: Determine Design Current
From earlier calculation:
Design Current (after margin) ≈ 700 A
🔹 Step 2: Select Current Density
Typical values used in Indian practice:
| Material | Current Density |
|---|---|
| Copper (Cu) | 1.2 – 1.6 A/mm² |
| Aluminium (Al) | 0.8 – 1.2 A/mm² |
🔹 Step 3: Calculate Required Busbar Area
✔ For Copper
✔ For Aluminium
🔹 Step 4: Select Standard Busbar Size
✔ Copper Option
Selected:
1 × (100 × 10 mm)
Area = 1000 mm²
✔ Provides safety margin
✔ Lower temperature rise
✔ Aluminium Option
Selected:
1 × (100 × 10 mm)
Area = 1000 mm²
👉 Practical rule:
Aluminium busbar area ≈ 1.5 times copper for better reliability.
✅ Short Circuit Withstand Check
Busbar must withstand system fault level.
Short circuit force depends on:
So higher fault current → stronger support required.
✔ Check panel fault level (e.g., 50 kA for 1 sec)
✔ Provide proper busbar supports
✔ Maintain phase spacing
✅ Busbar Spacing (Important)
Spacing depends on system voltage (415 V LT typical):
✔ Phase-to-phase clearance
✔ Phase-to-earth clearance
Proper spacing prevents flashover.
🔹 Comparison: Copper vs Aluminium
| Parameter | Copper | Aluminium |
|---|---|---|
| Conductivity | High | Lower |
| Size Required | Smaller | Larger |
| Cost | Higher | Lower |
| Weight | Heavy | Light |
| Maintenance | Low | Needs proper joints |
🔹 Practical Site Selection
✔ Use Copper (Cu) for:
- Critical systems
- HT/LT panels
- High reliability projects
✔ Use Aluminium (Al) for:
- Cost-sensitive projects
- Large distribution systems
🔹 Important Design Considerations
✔ Check temperature rise
✔ Provide proper spacing between phases
✔ Ensure proper insulation
✔ Use proper supports and clamps
✔ Maintain clearance inside panel
🔥 Professional Tip (Important for Your Work)
Since you are working in tender + execution, always:
✔ Mention both Cu & Al options in BOQ
✔ Compare cost vs performance
✔ Check client specification
✔ Verify termination (Al requires special lugs)
🔥Panel Design
Panel rating must be:
Earlier selected breaker = 800 A
✔ Panel Rating = 800 A to 1000 A🔹 Form of Separation
Common types:
- Form 1 – No separation
- Form 2 – Busbar separated
- Form 3 – Busbar + functional unit separation
- Form 4 – Full separation (highest safety)
✔ For commercial & industrial projects → Prefer Form 3 / Form 4
🔹 Panel Design Considerations
✔ Proper ventilation
✔ Cable alley space
✔ Top / Bottom cable entry
✔ Earthing busbar provided
✔ Proper gland plate thickness
✔ IP rating (IP42 / IP54 depending on location)
🔷 Basic Single Line Diagram (SLD)
Transformer (500 kVA)
|
ACB (800 A)
|
Busbar
/ | \
Feeder Feeder Feeder
| | |
Load Motor DB
👉 SLD helps in understanding system layout.
🔷 Important Design Considerations
✔ Use maximum demand, not connected load
✔ Apply diversity factor
✔ Include future load margin
✔ Consider derating factors
✔ Check voltage drop
✔ Verify short-circuit rating
✔ Ensure proper earthing
🔷 Common Mistakes in Electrical Design
❌ Using connected load instead of demand load
❌ Undersized cables
❌ Oversized breakers without calculation
❌ Ignoring voltage drop
❌ No fault level calculation
👉 These mistakes can lead to failure and safety risks.
🔷 Practical Tips for Engineers
For engineers working in site execution and design, always:
✔ Verify load calculation before design
✔ Cross-check cable size with standards
✔ Ensure proper protection coordination
✔ Maintain documentation for approval
✔ Follow safety standards strictly
🔷 Conclusion
Electrical design requires proper calculation, planning, and verification. A well-designed system ensures safety, efficiency, and long-term reliability of electrical installations.
This step-by-step approach helps engineers perform accurate design and avoid common errors in practical projects.
🔷 Total Connected Load Calculation (500 kW)
Assume a building with the following loads:
🔹 1. Lighting Load
- Total lights = 1000 Nos
- Each light = 40 W
Lighting Load = 1000 × 40
= 40,000 W = 40 kW
🔹 2. Socket Load
- Total sockets = 200 Nos
- Each socket = 200 W
Socket Load = 200 × 200
= 40,000 W = 40 kW
🔹 3. Air Conditioning Load
- Total AC units = 50 Nos
- Each AC = 2 kW
AC Load = 50 × 2
= 100 kW
🔹 4. Motor Load (Pumps, Lifts, etc.)
- Total motors = 10 Nos
- Each motor = 10 kW
Motor Load = 10 × 10
= 100 kW
🔹 5. Miscellaneous Load
Includes:
- Office equipment
- Kitchen equipment
- Spare loads
Misc Load = 50 kW
🔹 6. Future Provision
Future Load = 50 kW
🔷 Total Connected Load Calculation
Total Connected Load
= Lighting + Socket + AC + Motor + Misc + Future
= 40 + 40 + 100 + 100 + 50 + 50
= 380 kW
👉 Round off for design:
✔ Total Connected Load ≈ 400 kW
🔷 Example to Reach 500 kW
Add additional loads:
- Extra HVAC = 50 kW
- Additional equipment = 50 kW
Final Connected Load = 400 + 100 = 500 kW
✔ Total Connected Load = 500 kW

0 Comments