Here are the key electrical works as per CPWD guidelines in detail:
Electrical Wiring: Electrical wiring is the installation of conductors, cables, and other materials required for the safe and efficient distribution of electrical power within the building. CPWD guidelines specify the use of high-quality copper conductors, PVC insulated cables, and other materials that are resistant to fire, moisture, and mechanical stress. The wiring system must comply with all relevant Indian Standards and safety codes. CPWD guidelines also specify the type and rating of circuit breakers, switches, and other protective devices required for the electrical system.
Earthing: The CPWD guidelines require the installation of a robust earthing system to ensure the safety of the occupants and protect electrical equipment from damage due to electrical faults. The earthing system consists of a network of conductors buried in the ground, which is connected to the electrical system of the building. The earthing system must be designed and installed as per relevant Indian Standards to ensure low earth resistance and high conductivity.
Lighting: The CPWD specifications recommend the installation of various types of lighting fixtures such as LED lights, CFLs, and other lighting systems as per the requirements of the building. The lighting system must comply with all relevant Indian Standards and safety codes. The CPWD guidelines also specify the type and rating of switches, dimmers, and other control devices required for the lighting system.
Power Backup: The CPWD specifications recommend the installation of a reliable power backup system such as a generator, UPS, or inverter to ensure uninterrupted power supply to critical loads. The power backup system must be designed and installed as per relevant Indian Standards and safety codes. The CPWD guidelines also specify the type and rating of transfer switches, voltage stabilizers, and other protective devices required for the power backup system.
Fire Alarm Systems: The CPWD guidelines require the installation of a fire alarm system that is capable of detecting and alerting occupants of the building in case of a fire. The fire alarm system must comply with all relevant Indian Standards and safety codes. The CPWD guidelines specify the type and rating of detectors, control panels, and other components required for the fire alarm system.
Security Systems: The CPWD specifications recommend the installation of security systems such as CCTV cameras, access control systems, and intrusion detection systems to ensure the safety and security of the building and its occupants. The security system must comply with all relevant Indian Standards and safety codes. The CPWD guidelines specify the type and rating of cameras, sensors, control panels, and other components required for the security system.
Lightning Protection System: The CPWD guidelines recommend the installation of a lightning protection system to protect the building and its occupants from lightning strikes. The lightning protection system consists of a network of conductors and electrodes that are installed on the roof and other exposed surfaces of the building. The lightning protection system must be designed and installed as per relevant Indian Standards to ensure low impedance and high conductivity.
Here's a more detailed overview of the installation of HVAC systems, elevators, escalators, and other electrical equipment as per CPWD guidelines:
HVAC Systems: The installation of HVAC (heating, ventilation, and air conditioning) systems is an important electrical work in construction as it affects the overall comfort and energy efficiency of the building. CPWD guidelines specify the type and rating of HVAC equipment, including chillers, air handling units, ducting, and control systems. The guidelines also cover the design and installation of the electrical system required for HVAC equipment, such as power supply, grounding, and control wiring. The installation of HVAC systems must comply with all relevant Indian Standards and safety codes.
Elevators and Escalators: The installation of elevators and escalators is another key electrical work in construction, especially for high-rise buildings. CPWD guidelines specify the type and rating of elevators and escalators required for the building, as well as the location, size, and capacity of electrical equipment such as motors, controllers, and safety devices. The guidelines also cover the design and installation of the electrical system required for elevators and escalators, including power supply, grounding, and control wiring. The installation of elevators and escalators must comply with all relevant Indian Standards and safety codes.
Electrical Equipment: CPWD guidelines also cover the installation of various other electrical equipment required for the building, such as pumps, motors, compressors, and other machinery. The guidelines specify the type and rating of equipment required for the building, as well as the location, size, and capacity of electrical equipment such as motors, controllers, and safety devices. The guidelines also cover the design and installation of the electrical system required for the equipment, including power supply, grounding, and control wiring. The installation of electrical equipment must comply with all relevant Indian Standards and safety codes.
It is important to note that the scope of electrical works may vary depending on the size, type, and complexity of the building. Therefore, it is essential to consult the CPWD guidelines and seek professional advice from qualified electrical engineers and contractors to ensure the safe and efficient installation of electrical systems in the building.
Circuits |
|||||||||||||||||||||||||||||||||||
1. Load more than 1 KW shall be controlled by suitably rated MCB and cable size shall be decided as per calculations. 2. It is recommended to provide double pole MCB in proper enclosure as power outlet for window type AC units, geysers etc. 3. Power/light DBs shall be marked ‘P’ and ‘L’ respectively. |
|||||||||||||||||||||||||||||||||||
Lighting Circuit |
Per Circuit Not more than 10 Points of Lighting or Total 800 Watt which is less |
||||||||||||||||||||||||||||||||||
Power Circuit |
For Residential Per Circuit upto - 2 No of 16A Plug Socket - 3 No of 6A Plug Socket - 1 No 16A and 2 Nos 6A Plug Socket |
||||||||||||||||||||||||||||||||||
Power Circuit |
For Non Residential Per Circuit only 1 No of 6A/16A Plug Socket |
||||||||||||||||||||||||||||||||||
Plug Socket |
In Residential Wiring ,wiring of Socket outlet shall be done by copper Cable only |
||||||||||||||||||||||||||||||||||
Size of Wire |
For Lighting Circuit Smallest size of conductor shall be 1.5 Sq.mm For Power Circuit Smallest size of conductor shall be 4 Sq.mm Power circuit rated : More than 1 KW, Size as per calculation |
||||||||||||||||||||||||||||||||||
Classification |
Residential - GROUP A ( For Type I, II, III and Hostels), Conduit – 2.5 Mtr., Cable – 3 Mtr. GROUP B ( For Type IV and Above, Barracks)
Conduit – 3.5 Mtr., Cable – 4 Mtr. Non Residential - GROUP C ( For All Types- Offices, Hospitals, Lab, Library, etc.) Conduit – 4.5 Mtr., Cable – 5 Mtr. (Also used in Twin Control) · 5 % Wastage already taken in Rate. |
||||||||||||||||||||||||||||||||||
Conduit Size |
20 mm, 25 mm, 32 mm, 40mm can be used (As per requirement) |
||||||||||||||||||||||||||||||||||
GI Box |
1 Module - 75mm x 75mm 2 Module - 75mm x 75mm 3 Module - 100mm x 75mm 4 Module - 125mm x 75mm 6 Module - 200mm x 75mm 8 Module - 125mm x 125mm 12 Module - 200mm x 150mm |
||||||||||||||||||||||||||||||||||
Metal Box |
60 mm deep can be used |
||||||||||||||||||||||||||||||||||
MCB |
SP - 6A to 32A, 240/415V, 10 KA, “C” Curve SPN - 6A to 32A, 240/415V, 10 KA, “C” Curve DP - 6A to 32A, 240/415V, 10 KA, “C” Curve TP - 6A to 32A, 240/415V, 10 KA, “C” Curve TPN - 6A to 32A, 240/415V, 10 KA, “C” Curve |
||||||||||||||||||||||||||||||||||
TP&N MCB |
(31, 63, 100, 125, 160, 200, 315, 400 )A |
||||||||||||||||||||||||||||||||||
MCCB Rating 3 Pole |
(100,125,150,200,250,315,400,500,630,800)A; (16, 25, 35, 50) KA |
||||||||||||||||||||||||||||||||||
MCCB Rating 4 Pole |
(100,125,200,250,400,630,800)A; (30,36,50) KA |
||||||||||||||||||||||||||||||||||
Isolator |
DP - (40, 63)A 4P - (40, 63, 100)A |
||||||||||||||||||||||||||||||||||
RCCB (30mA) |
DP - (25, 40, 63)A 4P - (25, 40, 63)A |
||||||||||||||||||||||||||||||||||
MCB DB |
(6, 8, 12, 16 ) Way Double Door – Single pole & Neutral (SPN) Horizontal Type: Way Double Door –Three pole & Neutral (TPN) 4 (4+12) 6 (4+18) 8 (4+24) Vertical Type: Way Double Door – Three pole & Neutral (TPN) 4 (4+12) 8 (4+24) 12 (4+36) |
||||||||||||||||||||||||||||||||||
Isolator |
DP - (40, 63)A 4P - (40, 63, 100)A |
||||||||||||||||||||||||||||||||||
TPN Industrial Type Socket |
· TPN (20, 30 )A · Industrial type Socket Outlet with Plug top and metal chained cover · TP MCB : 6A to 32A, 240/415V, 10 KA, “C” Curve |
||||||||||||||||||||||||||||||||||
Rising Mains |
· 200 A (Isc – 15 KA for 1 Second) · 300 A (Isc – 20 KA for 1 Second) · 400 A (Isc – 25 KA for 1 Second) · 600 A (Isc – 45 KA for 1 Second) · 800 A (Isc – 50 KA for 1 Second) |
||||||||||||||||||||||||||||||||||
Tap OFF Box
|
TPN Tap OFF Box · One Way - (16, 32, 63, 200, 315, 400)A · Two Way – (16, 32,63)A · Four Way – (16, 32,63)A · Six Way - (16, 32,63)A · Eight Way - (16, 32,63)A |
||||||||||||||||||||||||||||||||||
Colour Coding |
Following colour coding shall be followed in wiring: Phase : Red/Yellow/Blue.(Three phase wiring) Live : Red (Single phase wiring) Neutral : Black Earth : Yellow/Green. |
||||||||||||||||||||||||||||||||||
Plug Socket |
|||||||||||||||||||||||||||||||||||
1. The third pin shall be connected to earth through protective (loop earthing) conductor. 2. 2 pin or 5 pin sockets shall not be permitted to be used, 3. Rating above 1KW shall be of industrial type with associated plug top and controlling MCB. |
|||||||||||||||||||||||||||||||||||
Plug Socket |
6A - rated at 100W 16A - be rated at 1000W |
Unless the actual values of loads are specified.
|
|||||||||||||||||||||||||||||||||
5A/6A or 15A/16A Socket shall be installed at following heights: For Non Residential building 23cm above floor For Kitchen 23cm above Platform and away from stove and sink. For Bathroom not Socket is provided, MCB/IC will be 2 metre from fixed appliance and at least 1 metre away from Shower |
|||||||||||||||||||||||||||||||||||
IS Standard |
|
||||||||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||
Switch Board / D.B |
|||||||||||||||||||||||||||||||||||
1. Switchboards are to be located in common areas like corridors, lobby etc. and not to be located in locked room. 2. Switch box or regulator box shall be made of metal on all sides, except on the front. In the case of cast boxes, the wall thickness shall be at least 3 mm and in case of welded mild steel sheet boxes, the wall thickness shall not be less than 1.2 mm (18 gauge) for boxes upto a size of 20 cm x 30 cm, and above this size 1.6 mm (16 gauge) thick MS boxes shall be used. 3. Follows |
|||||||||||||||||||||||||||||||||||
Operating Rod |
Operating Rod/Handle of Distribution Board at the height of min 2 metre |
||||||||||||||||||||||||||||||||||
D.B Clearance |
Clear Distance in front of Switch Board/D.B shall be min 1 metre |
||||||||||||||||||||||||||||||||||
Switch Box |
Switch Box or Regulator Box shall be mounted with their bottom 1.25 metre from floor level |
||||||||||||||||||||||||||||||||||
Fan |
|||||||||||||||||||||||||||||||||||
Fan Box |
1. For Fan Hook in concrete roof 12mm dia MS Rod in ‘U’ Shape, horizontally Leg at Top at least 19 cm on either side. 2. Circular Box Type Fan Clamp- 16SWG MS Sheet As Per CPWD 10.18 (CIVIL): Providing and fixing circular/ Hexagonal cast iron or M.S. sheet box for ceiling fan clamp, of internal dia 140 mm, 73 mm height, top lid of 1.5 mm thick M.S. sheet with its top surface hacked for proper bonding,top lid shall be screwed into the cast iron/ M.S. sheet box by means of 3.3 mm dia round headed screws, one lock at the corners. Clamp shall be made of 12 mm dia M.S. bar bent to shape as per standard drawing. Specification: Civil Volume 1 ; 10.14 |
||||||||||||||||||||||||||||||||||
Capacity of a Ceiling fan |
=55D m3/min ,D= the longer dimension of a room |
||||||||||||||||||||||||||||||||||
Height of fan blades above the floor |
= (3H + W)/4, where H is the height of the room, W is the height of work plane. |
||||||||||||||||||||||||||||||||||
Minimum distance between fan blades and the ceiling |
0.3 metre. |
||||||||||||||||||||||||||||||||||
Ceiling Fan Rating |
· 60W, Energy Efficient fans with BEE 3-5 star rating or complying with IS 374: 1979, shall be used. The minimum service value of fans shall be 3.5 m3/min/W and air delivery 200 m3/min. · BEE 5 star rated Ceiling fan with Brush Less Direct Current (BLDC) motor |
||||||||||||||||||||||||||||||||||
IS Standard |
Ceiling Fan - IS: 374/1979 Exhaust Fan - IS: 2312/1963 Electronic fan regulator - IS:11037/1984 |
||||||||||||||||||||||||||||||||||
Junction Box |
|||||||||||||||||||||||||||||||||||
Junction Box |
Depth of Junction Box shall be min 65mm in slab and other places as per IS 2667 : 1988 |
||||||||||||||||||||||||||||||||||
Fish Wire |
|||||||||||||||||||||||||||||||||||
Fish Wire |
GI fish wire of 1.6mm/1.2mm (16/18 SWG) shall be used along with the laying of the recessed pipe. |
||||||||||||||||||||||||||||||||||
Earthing |
|||||||||||||||||||||||||||||||||||
Items Required |
GI Pipe Earthing · GI Pipe 40mm (Medium Class) – 4.5 Mtr · Cover Plate hinged to frame with locking Arrangement · 40mm to 20mm Reducer · Funnel · GI Nuts Through Bolts with washer · Charcoal – 64 Kg · Salt- 5 Kg GI Plate Earthing · GI Plate– 600mm x 600mm x 6mm Thick · GI Pipe 20mm (Medium Class) – 2.7 Mtr · Cover Plate hinged to frame with locking Arrangement · Funnel · GI Nuts Through Bolts with washer · Charcoal – 96 Kg · Salt- 5 Kg Copper Plate Earthing · Copper Plate– 600mm x 600mm x 3mm Thick · GI Pipe 20mm (Medium Class) – 2.7 Mtr · Cover Plate hinged to frame with locking Arrangement · Funnel · GI Nuts Through Bolts with washer · Charcoal – 96 Kg · Salt- 5 Kg |
||||||||||||||||||||||||||||||||||
GI Wire |
6 SWG (0.147 kg/mtr) |
||||||||||||||||||||||||||||||||||
Copper Wire |
8 SWG (0.117 kg/mtr) |
||||||||||||||||||||||||||||||||||
GI Strip |
25mm x 5mm (1.0 kg/mtr) |
||||||||||||||||||||||||||||||||||
Copper Strip |
50 mm x 5mm (2.30 kg/mtr) |
||||||||||||||||||||||||||||||||||
Lightning Conductor |
|||||||||||||||||||||||||||||||||||
Items Required |
Lightning Finial · Lightning Finial (GI) -25mm Dia x 300 mm Long · Steel Fastener - 6mm x 75mm GI Tape - 20mm x 3mm thick (0.461 kg/mtr) - 32mm x 6mm thick (1.475 kg/mtr) GI Saddle - 20mm x 3mm thick PVC Fastener – 40mm long Iron Screws - 35mm x 6mm thick
|
||||||||||||||||||||||||||||||||||
MV/HV Cable Laying |
|||||||||||||||||||||||||||||||||||
Items Required |
Direct in Ground: For 100 Metres · Brick - 874 Nos + 44 Wastage(5%) = 918 Nos · Fine Sand – 8.76 CUM For Additional one Nos. · Brick - 874 Nos + 44 Wastage(5%) = 918 Nos · Fine Sand – 5.0 CUM On Wall Surface: Upto 35 Sq.mm · GI Saddle - 19mm x 0.55mm for Conduit Above 35 Sq.mm · Nuts & Bolts - 32mm x 8mm · Flat Iron – 20/25/40mm x 3mm · Steel Fastener - 6mm x 75mm |
||||||||||||||||||||||||||||||||||
MV Cable Jointing & End Termination |
|||||||||||||||||||||||||||||||||||
Items Required |
· Brass Compression Gland for 2 x 6 Sq. mm (19 mm) 1.1 kv cable & Al lugs for 6 Sq.mm cable. Same for Another Size · Jointing Kit |
||||||||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||
Installation Testing & Commissioning Charges as Per DSR 2018 |
|||||||||||||||||||||||||||||||||||
· 1.41 , 1.42 – For Lighting Fixture · 1.44, 1.45 – For Fan |
|||||||||||||||||||||||||||||||||||